We invite you to familiarize yourself with the progress of works in the Cieszyńska 9 investment.
Works related to the ground level of building A (ceiling over the underground garage) - eastern part of the building are nearing completion.
We started reinforcement and formwork of the walls of the ground floor in the western part of building A.
At the same time, garage walls under building C and a foundation plate under building B.
CONSTRUCTION SITE NEWS
Feb 22, 2022
CIESZYŃSKA 9